Waste management enterprise pursuant to §§ 56 and 57, Waste Management Act (KrWG)
Residual waste volume (100% load) | 4 x 22 t/h |
Residual waste volume per year | 650,000 t |
Total investment | 250 million Euros |
Supplier/general contractor | AE&E Inova GmbH (formerly Alstom Power Boiler GmbH) |
Waste bunker | 2 x 12,000m³; (2 x 6,000 t) 2 deep bunkers with 6 dumping stations each 4 gantry cranes with hydraulic grippers |
Boilers | 4-step natural circulation boiler vertical with drum heating surface 7,130m² each steam quantity 77.6 t/h each |
Turbine | 2 extraction condensing turbines 2 x 33.6 MW gross output |
Grate | 4 units each 9.7m long and 6.9m wide water- and air-cooled feed grate |